Haroli/Una, October 30 (Rajveer Chopra):- According to a press release issued by the Himachal Pradesh State Electricity Board Limited, scheduled testing and essential repair work will be carried out at the 132 kV substation Una on November 2, 2026 (Monday). Consequently, electricity supply at the 132 kV substations Una and Tahliwal will remain disrupted from 9 AM to 5 PM.
During this period, electricity supply will be affected in areas connected to the 132 kV Him Textile, 132 kV Kaslai, 33 kV Basal, 33 kV Haroli, 33 kV Gagret, 33 kV Bangana and 11 kV Peer Nigah feeders falling under the 132 kV substation Una.
Similarly, electricity supply will also remain suspended from 9 AM to 5 PM in areas covered by the 33 kV HM Steel Industry, 33 kV Surbhi Steels, 33 kV substation Tahliwal, 33 kV substation Santoshgarh, 33 kV substation Gondpur and 11 kV Industrial Area feeders under the 132 kV substation Tahliwal.
Assistant Engineer of the Board, Engineer Deepak Kumar, while providing this information, has appealed to consumers in the affected areas to extend their cooperation.